GC Update, October 14, 2016

The tower crane is completely disassembled and has been removed from the site.
16-1014_site_progress__page_03
16-1014_site_progress__page_04

Slab openings, where the crane assembly once stood, remain open and await scheduling for in-fill.
16-1014_site_progress__page_05

Structural steel is being marked and prepared for internal wall framing, ceiling and finish supports.
16-1014_site_progress__page_06
16-1014_site_progress__page_07
16-1014_site_progress__page_08
16-1014_site_progress__page_09

Second floor concrete pours are underway
16-1014_site_progress__page_10
16-1014_site_progress__page_11

Fireproofing of structural steel is being applied.
16-1014_site_progress__page_12
16-1014_site_progress__page_13
16-1014_site_progress__page_14
16-1014_site_progress__page_15
16-1014_site_progress__page_16

Overall Progress Photos
16-1014_site_progress__page_17
16-1014_site_progress__page_18
16-1014_site_progress__page_19
16-1014_site_progress__page_20

GC Update, September 16, 2016

An overall shot of the project site.  The scaffolding and concrete work in the foreground is part of the Developer’s new parking garage structure.  The multi-level steel structure further back in the photo is the store that this web site is following the construction of.  To the left of of the store site you can see the old Macy’s which is at the end of the existing mall structure.160916_nordstrom_utc_361-site_progress_page_19

The General Contractor finally has a new “permanent” office trailer on site.  This is where all construction personnel will convene for the weekly OAC meetings and where the project design team is able to establish temporary office space while they are at the construction site.
160916_nordstrom_utc_361-site_progress_page_03

Concrete curb pouring is in progress.
160916_nordstrom_utc_361-site_progress_page_04

160916_nordstrom_utc_361-site_progress_page_05

160916_nordstrom_utc_361-site_progress_page_06

160916_nordstrom_utc_361-site_progress_page_07

160916_nordstrom_utc_361-site_progress_page_08

160916_nordstrom_utc_361-site_progress_page_09

160916_nordstrom_utc_361-site_progress_page_10

Preparing for the first floor slab pour. Reinforcing mesh installed.
160916_nordstrom_utc_361-site_progress_page_11

160916_nordstrom_utc_361-site_progress_page_12

Metal stair installations nearing completion. After all steel assemblies are in completed concrete will be poured on the top of the metal structure to form to treads and landings. The risers will remain as uncovered painted steel.
160916_nordstrom_utc_361-site_progress_page_13

160916_nordstrom_utc_361-site_progress_page_14

160916_nordstrom_utc_361-site_progress_page_15

Adjacent Developer Construction Progress
160916_nordstrom_utc_361-site_progress_page_17

160916_nordstrom_utc_361-site_progress_page_18